Permit Timeliness data collection is in response to a State Auditor’s Performance Audit and RCW 43.42A. Each regulatory agency developed a plan to improve permit clarity, predictability, and timeliness. Each agency considers the customers experience to ensure permit assistance is simple to use, easy to access, and designed in a customer-friendly manner. Agencies report progress to the Governor’s Office for Regulatory Innovation and Assistance (ORIA). ORIA prepares and distributes reports, with participation from the State Auditor’s Office and Results Washington. See latest report here: https://www.oria.wa.gov/ORIA-2020-PermitTimelinessProgressReport.pdf.
Estimated Time Required By the Agency to Process a Permit Application (Definition)Average days from Receipt to Complete: Not available under EO 25-03 methodologyMaximum days from Receipt to Complete: Not available under EO 25-03 methodologyEstimated Time Required By the Agency to Issue a Permit Decision (Definition)Average days from Complete Application to Decision: 68Maximum days from Complete Application to Decision: Not available under EO 25-03 methodologyThe general order permits are not tracked individually so the results are combined for General Order of Approval for: Asphalt Plants, Auto Body Shops, Concrete Batch Plants, Dairy Manure Anaerobic Digesters, Gas Fired Emergency Electrical Generators, Perchloroethylene Dry Cleaners, Small Boilers Using Natural Gas, Propane, or Diesel Fuel, and Stationary or Portable Rock Crushers.
(Summary results based on 2 submittals in 2025)